Jump to main content

Online Feature Articles for Construction Professionals - Engineers

Case StudyOnline Feature Articles for Construction Professionals - Engineers
Slide 1

Amanda, a senior engineer heading a project section of a government works department, supervised several engineers who were each in charge of one civil engineering project. Amanda heard from another colleague that Stephen, one of the engineers, and his site supervisory team had lavish meals and gambled frequently with staff of the main contractor and the subcontractors under their supervision.

Slide 2

Amanda expressed her concern to Stephen about his frequent social gatherings with the contractor and the subcontractors. Stephen defended that the team had been working closely with the contractor and the subcontractors in previous projects. These social activities helped the team build mutual trust and collaborative relationship, which would ultimately enhance work efficiency.

Slide 3

Amanda further questioned Stephen that some works progress records which should be prepared by the contractor were missing or submitted late. Stephen assured Amanda that the construction works had been carried out in an orderly manner and commented that record was just a mere formality. Due to the tight construction schedule, the contractor did not have time to prepare the records and promised to complete the tasks later. He asked Amanda not to worry as the contractor was a trustworthy partner. On the other hand, Stephen allowed the contractor to upload photos of other works locations to the Digital Works Supervision System when preparing the inspection records so as to save time.

Slide 4

Amanda did not pursue any further as she was busy and relied largely on Stephen and his team for the daily supervision of the project. Her priority concern was to complete the project on time without trouble.

Slide 5

Because of bad weather and repeated rectification works, the works progress began to fall behind schedule. Stephen discovered from test reports that the strength of the concrete for some structural elements did not meet the contract requirements. He brought up the issue to the site agent of the contractor. The site agent told Stephen that the concrete strength was just marginally below the required standard and would not affect project quality; whereas further rectification works would delay the project. While Stephen was still wondering whether he should pursue further, the site agent mentioned that his project manager, Ernest, would like to invite him to a dinner at a private club at the coming weekend.

Slide 6

Over the dinner, Ernest asked Stephen not to worry about the project and assured him that the overall structure would still be safe. Informed by the site agent that Stephen was heavily indebted because of big losses in stock investment, Ernest offered to lend him $300,000 to overcome his financial difficulty. Stephen initially declined Ernest's offer but later considered it a feasible solution as his debts had accumulated substantially.

Last update: 
Level AA Conformance to Web Content Accessibility Guidelines 2.1